Leading lights shine bright in Blackpool bridge work

 

Ilyass Meslek, engineer at CCL, a specialist in engineered solutions for structures, discusses the design considerations for a road-over-rail replacement project in Blackpool where CCL was brought in to advise on the bridge bearing requirements during the early design stages.

With its kiss-me-quick hats, world famous tower and seven-mile stretch of sandy beach, Blackpool is a town built on tourism. So when a road-over-rail bridge needed to be replaced to enable electrification of the railway line below, it was vital that the job was delivered during the tourist ‘off season’ to minimise the commercial impact on the holiday hotspot. Moreover, Blackpool’s holiday season is longer than most. Beginning with the Easter break, it continues right through to early November when the celebrated illuminations along the Golden Mile are switched off to make way for Christmas decorations.

”Local
 

The bridge in question is on Plymouth Road. In addition to being on a major route into the town, it is in a residential area and above a busy rail line, which, aside from two weekend closures, had to remain operational throughout the programme.

The reason for the bridge replacement was the electrification of the rail line as part of a programme of works across the North West of England, creating the need for a larger clearance between the railway line and the road above. Blackpool Council considered a number of strategies to minimise the impact of the works, including the possibility of jacking up the existing bridge or lowering the section of line; however, the close proximity of a station to the relevant section of line ruled out the lowering option and the poor condition of the bridge, due to its age and the corroded steel within the structure, meant that jacking it up was not a viable option either. The only feasible strategy was to develop a programme of works that would enable replacement of the structure, including raising of the soffit, within the five-month off season window with works taking place during overnight rail line possessions.

Site preparation and safety

Designed by Wilde Consulting Engineers and delivered by Story Contracting for Network Rail, in association with Blackpool Council, the project required removal of the existing three-span deck, which equated to around 1,000 tonnes of concrete and steel.

Because the road closure was limited to the tourist off season, Story Contracting worked closely with Blackpool Council to develop a programme that enabled diversion of services, including high voltage, low voltage, telecoms, fibre, gas, street lighting and a 750mm water main prior to demolition in a single phase operation. This was achieved by designing a new edge beam to the eastern side of the existing bridge which could be installed pre-demolition, creating an additional lane so that two lanes of traffic could be maintained during the service diversions.

Once this was in place, the diversions were carried out as part of a three-month enabling phase. This solution provided a cost saving of £500,000 compared to the original plan for a two-stage diversion, as well as reducing programme risk.

A temporary service bridge was also constructed during this enabling phase to maintain pedestrian access throughout the scheme, thereby avoiding any requirement for a level crossing and reducing any risk to public safety associated with the scheme.

Due to the railway line below, the demolition works to the bridge could only be carried out at night when there were no train services and the line could be isolated. This gave the contractor an operational window of just six hours during the week and eight hours at weekends. Story Contracting used hydraulic bursting demolition techniques to minimise noise during the demolition phase, due to the close proximity of residential properties, and monitored noise throughout the programme.

Bridge construction

To ensure construction of the new bridge could be carried out over a minimal road closure period, the new bridge deck was constructed with 18 prestressed precast concrete beams per span, with 54 prestressed precast concrete beams in total for the three spans. The new bridge deck was constructed using the existing abutments and the concrete beams were lowered into position following installation of 108 custom-designed and manufactured elastomeric bridge bearings, using a 1,000-tonne lattice crane. With a combined weight of 600 tonnes, the precast beams were installed in day and night time operations over just two 54-hour weekend railway possessions. CCL was brought in to advise on the bridge bearing requirements of the project by Wilde Consulting during the early design stages of the project to ensure that the maximum vertical loading, transverse force and rotational movement could be achieved within the constraints of the bearing design. As a refurbishment project utilising the existing abutments and piers, the space available for the bearing shelf and, consequently, the bearings, was limited to the existing structural parameters.

The existing structure also influenced the bridge design itself. Plymouth Road Bridge is a three-span bridge with the largest span in the centre, supported by a pair of central piers. If all three spans had been the same length, the replacement bridge could have been designed as a continuous structure. However, because the spans were different lengths, they were designed as semi-discrete structures to allow rotational movement at the piers. An infilled slab ties the three spans together while each span can act independently.

Among the other key design criteria was the requirement for a high-containment parapet running the whole span of the bridge to safeguard pedestrians and mitigate the risk of any vehicles falling onto the railway line in the event of a road traffic accident. This parapet had to be factored into the design considerations for the bridge bearings because it increased the forces for the edge beams of the central span.

Creating the central span

The maximum force requirements for each element of the bridge were generated in structural analysis software and, for the majority of the 108 bridge bearings, the design requirements were for vertical forces of up to 750kN, transverse loading of up to 35kN and rotation of up to 0.006 radians.

The precast bearing shelf was fabricated in three sections for ease of transport and CCL had to design the bearings to fit the dimensions of the shelf, which were restricted by the abutments and pillars.

Speed of manufacture was also critical, as the bearings had to be installed within the prescribed window in the schedule, in line with agreed railway possessions. The CCL team developed a series of design iterations for the bearings so that the design and delivery team could agree the best-fit solution for the project. The bearings were then manufactured and delivered to site with guidance on the most appropriate fixing methodology.

Once the bearing shelves were in position, surveyors marked out the locations for each bearing across the length of the shelf and each bearing was secured in place using an epoxy mortar.

With all the bearings in place, the precast beams were lowered into position onto the bearings with a narrow void between each beam. All the beams were cast with transverse details to enable steel ties to be threaded through the new structure, tying the beams together. A concrete pour, totalling 800 tonnes of concrete poured in situ, filled the void between the beams to create a single, monolithic structure and a level deck 150mm above the surface of the beams. A bridge deck waterproofing surface was then sprayed onto to the concrete deck prior to installation of the road surface.

Early completion

Throughout the project, keeping the programme on track was business critical for both the contractor, Network Rail and Blackpool Council and the project was successfully completed three weeks ahead of schedule.

Bridges 2018 takes place on Wednesday 14th March at the Ricoh Arena, Coventry. Over 350 attendees have already confirmed their place at the conference, which features a sold-out exhibition hall. Register today at https://bridges.tn-events.co.uk

Register now for full access


Register just once to get unrestricted, real-time coverage of the issues and challenges facing UK transport and highways engineers.

Full website content includes the latest news, exclusive commentary from leading industry figures and detailed topical analysis of the highways, transportation, environment and place-shaping sectors. Use the link below to register your details for full, free access.

Already a registered? Login

 
comments powered by Disqus
 
 
transport network jobs

CIVIL/STRUCTURAL ENGINEER

Torridge District Council
Up to £34,106 per annum plus relocation package up to £8,000
Looking for an experienced civil/structural engineer providing strategic feasibility and design advice to the authority Bideford, Devon
Recuriter: Torridge District Council

Highway Project Engineer

City of London
Up to £42,870 per annum (inclusive of London Weighting) depending upon performance.
The Department of Built Environment is responsible for the delivery of highway and drainage schemes within the City of London London (Central), London (Greater)
Recuriter: City of London

Graduate Transport Planner

Cambridgeshire County Council
£17,681 - £23,111
EXCITING GRADUATE OPPORTUNITY Cambridgeshire
Recuriter: Cambridgeshire County Council

Engineer Maintenance

Liverpool City Council
£32,233 - £37,107
Liverpool City Council are looking to recruit an Engineer Maintenance Liverpool, Merseyside
Recuriter: Liverpool City Council

Tree Services Programme Manager

Nottingham City Council
£37,107
You will be responsible for the management and maintenance of the Council's trees and woods, and will provide professional advice to others Woodthorpe, Nottingham
Recuriter: Nottingham City Council

Transport Coordinator

Camden London Borough Council
£32,473 to £37,670
We have an exciting opportunity for 2 highly customer focused Transport Coordinators to work in the busy Camden Transport Team. Camden, London (Greater)
Recuriter: Camden London Borough Council

Highway Electrical Supervisor (Highway Maintenance)

Sefton Metropolitan Borough Council
£24,657 to £28,221
The post will support two Senior Lighting Engineers in leading and contributing to the delivery of the Street Lighting function for the Authority Bootle, Merseyside
Recuriter: Sefton Metropolitan Borough Council

Flood Risk Management Engineer

London Borough of Bexley
£31,353 to £36,876
We are currently seeking a Flood Risk Management Engineer who will have a lead role with the Flood Risk and Development Team Bexley (City/Town), London (Greater)
Recuriter: London Borough of Bexley

Senior Engineer (Traffic Signal Improvements)

Lincolnshire County Council
£34,106 - £38,052
This is a superb opportunity to lead, motivate and inspire our engineering team working on traffic signal improvement projects. Lincolnshire
Recuriter: Lincolnshire County Council

Senior Engineer (Traffic Signal System and Operations)

Lincolnshire County Council
£34,106 - £38,052
This is a superb opportunity to lead, motivate and inspire our engineering team working on traffic signal systems and operations. Lincolnshire
Recuriter: Lincolnshire County Council

Principal Engineer (Traffic Signals)

Lincolnshire County Council
£42,806 - £49,441
Do you want to lead, manage and motivate a team of engineers working at the cutting edge of technology? Lincolnshire
Recuriter: Lincolnshire County Council

Principal Nuisance Control Officer

Brent Council
£38,040 - £40,086 p.a. inc. + £4,800 shift allowance p.a.
Salary range
Recuriter: Brent Council

Rights of Way Search Officer - Highways Services

Bridgend County Borough Council
£7,188 - £7,327 per annum
We are seeking someone to assist in maintaining, developing and promoting the Definitive Map for Bridgend Bridgend (Pen-y-bont ar Ogwr)
Recuriter: Bridgend County Borough Council

Countryside Access Maintenance Officer - Highways Services

Bridgend County Borough Council
£12,644 - £13,015 per annum
We are seeking someone to assist in ensuring that the local rights of way network is protected, well maintained and enjoyed... Bridgend (Pen-y-bont ar Ogwr)
Recuriter: Bridgend County Borough Council

Principal Transport Officer

Cambridgeshire County Council
£37,320 to £40,198
The role will require close dialogue with developers and their agents and necessitate strong partnership working with District Councils... Cambridge, Cambridgeshire
Recuriter: Cambridgeshire County Council

Project Engineer

North Yorkshire County Council
up to £33,136
Are you a qualified Highways Project Engineer? Would you like to work in the famous James Herriot area of natural beauty? North Yorkshire
Recuriter: North Yorkshire County Council

Highways Officer Highways and Transport

North Yorkshire County Council
£28,2281 p.a.
Are you someone who is looking to progress their career with one of the most highly regarded highway services in the country? North Yorkshire
Recuriter: North Yorkshire County Council

Regional Strategy Officer

North Yorkshire County Council
Band 15 – up to £41,846
Are you an experienced Transport Planner? Do you have exceptional communication skills to build relationships within teams? North Yorkshire
Recuriter: North Yorkshire County Council

Area Manager

North Yorkshire County Council
up to £53,113 p.a. winter allowance plus 10% one off additional payment for exceptional candidates
Four Area Highway Managers roles available York, North Yorkshire
Recuriter: North Yorkshire County Council

Transport Planning Officer – Major Development Applications

Somerset County Council
£33,136 to £37,107
We have a fantastic opportunity in Somerset within our Highways Development Management team. Taunton, Somerset
Recuriter: Somerset County Council